Startup Conditions for Slurry Pumps

Oct 03, 2026

Leave a message

The conditions for starting a slurry pump are as follows:
(1) Perform a standard pre-startup inspection of the slurry pump.
(2) Verify that the slurry pump piping is clear, the designated thickening tank is selected, the water inlet valve is open, the selected thickener is in operation, the thickener's slag discharge and flushing valves are closed, and the slag discharge pump is set to interlock mode.
(3) Ensure the slag pit is free of debris and the water level is above 1.2 meters.
(4) Confirm that the agitator associated with the slurry pump has been started and is operating normally.
(5) Adjust the slurry pump's variable-frequency drive (VFD) to a setting below 10%.
(6) Start the slurry pump via the Distributed Control System (DCS); once the outlet valve is fully open, gradually adjust the VFD frequency to meet the water volume requirements of the reclaimed water tank.
(7) After the slurry pump has started successfully, monitor the coordination between the slurry pump discharge and the reclaimed water pump discharge, as well as the water temperature in the slag extractor.